Horizontal Soil Vapor Extraction and Horizontal Air Sparge Well Case Study- Installation to remediated site closure

Horizontal Wells allow Rapid Clean-up of
R&D Facility Gasoline Release

Background

A Research and Development facility in central New Jersey released several thousand gallons of gasoline to the subsurface. Environmental investigations revealed that approximately 80% of the phase separated plume existed below the building. Uninterrupted operation and prevention of vapor intrusion in the facility were key factors that dictated an alternative approach to the remedial strategy. Hudson Environmental Services, Inc. of Matawan, New Jersey completed the remedial investigation, assessed remedial alternatives and proposed a remedy. Horizontal air sparge (AS) and horizontal soil vapor extraction (SVE) with vapor treatment utilizing catalytic oxidation was the recommended and selected remedy.

The Challenge Presented

Two technical approaches were available for the horizontal air sparge (AS) and horizontal soil vapor extraction (SVE) system orientation: install a series of multiple vertical wells (a number would be required inside the building) with an interconnecting subsurface piping network, or install three horizontal wells, which would pass beneath the building. Feasibility and financial analyses indicated that the horizontal well system would not disrupt business operations, be less expensive and more efficient than the traditional vertical well approach. Directional Technologies, Inc. was engaged to install the horizontal wells.

Directional Technologies at Work: Our Solution

Pilot testing and subsurface characterization provided data enabling Directional Technologies to design two horizontal air sparge wells and one horizontal soil vapor extraction well. The horizontal air sparge and horizontal soil vapor extraction wells were designed to operate at 250 cubic feet per minute (CFM). The system design included a catalytic oxidizer to destroy hydrocarbon vapors extracted from the horizontal soil vapor extraction well. The NJ Department of Environmental Protection (NJDEP) approved the remedial design following the first design submittal. Underground utilities, building footings and other subsurface structures were identified and surficially marked out prior to well installation. Directional Technologies designed the horizontal well trajectories to avoid these buried structures.
Directional Technologies used a Ditch Witch Directional Boring System to directionally drill the horizontal wells and has used this drill rig to successfully drill bores up to 12 inches in diameter and 700 feet long; while compact in size, it is extremely powerful. The directional drill rig’s compact size allows it to be used in relatively confined areas and the rubber tracks exert minimal ground pressure, minimizing risk of damage to pavement and turf. The power and two speed spindle rotation capability enabled the rig to successfully penetrate both hard and soft soil conditions encountered at the site (fine sands, silts and clays).

Directional Technologies advanced each pilot hole to the specified depth and horizontal termination point using a spade bit. Drill bit X-and-Y axis directional control and operational temperature was provided by a hand-held surface walk-over radio detection instrument. The instrument receives continuous radio signals from a battery-powered instrumentation module contained in a length of drill pipe located directly behind the drill bit. Regularly measuring drill bit temperature is important to ensure that drilling fluids are circulating through the drill bit, especially when drilling in rock.
Directional Technologies enlarged each pilot hole to a diameter of 6.5 inches using a spiral-cutting-configured back reamer drill bit designed to minimize formation displacement and compaction. Cement grout pumped through tremie pipes formed a seal in the annular space between the riser and formation. Directional Technologies developed the horizontal wells with water and a proprietary additive to flush out drilling fluid that may have entered the formation during the horizontal drilling process. Directional Technologies installed two identical horizontal air sparge wells configured as follows: 4 inch diameter, riser length: over 500 feet, screened interval: 260 feet, installed depth: 22 feet below ground surface, 7-9 feet into the water table. The single horizontal soil vapor extraction well was configured and installed as follows: 4 inch diameter, riser length: over 480 feet, screened interval: 240 feet, installed depth: 8 feet below ground surface (5-7 feet above the water table). The horizontal wells were constructed of SDR-11, a high density polyethylene (HDPE) product; Directional Technologies validated the choice of this choice product via detailed computer modeling. Modeling further dictated the need for multiple slot-zones in the horizontal soil vapor extraction well screen due to the multiple design goals of uniform air sparging and extraction and a flow rate of 250 CFM to the catalytic thermal oxidizer.

Results that Reward

The time required to achieve site remediation can be conservatively calculated from the quantity of oxygen delivered to the site by the remediation system. Directional Technologies designed/installed each horizontal air sparge well to deliver approximately 2 pounds per minute of oxygen to the subsurface, or a total of 4 pounds per minute. At this oxygen delivery rate Directional Technologies estimated that site cleanup would be accomplished in approximately one year. The horizontal air sparge and horizontal soil vapor extraction system operated from March 1999 to October 2000 and removed approximately 17,000 pounds of gasoline. The separate phase gasoline plume under the building was completely eliminated. This resulted in the NJDEP approving” no further action” for soils.

Posted in Symposium & Conference | Leave a comment

Enhanced Delivery of Potassium Permanganate Using Horizontal Wells

Paper E-036, in: Bruce M. Sass (Conference Chair), Remediation of Chlorinated and Recalcitrant Compounds—2008.Proceedings of the Sixth International Conference on Remediation of Chlorinated and Recalcitrant Compounds (Monterey,CA; May 2008). ISBN 1-57477-163-9, published by Battelle, Columbus, OH, www.battelle.org/chlorcon
 

William M. Moran (The Shaw Group, Trenton, New Jersey) George Losonsky, Ph.D., P.E. (Losonsky & Associates, Baton Rouge, Louisiana)

ABSTRACT: Commercial re-development of environmentally impacted land can require aggressive remediation schedules. Effective delivery of in-situ remediation agents is a key factor in meeting deadlines. In situ chemical oxidation (ISCO) was used to remove drycleaning solvent from the subsurface beneath a large property in the Mid-Atlantic region of the United States. Directional drilling technology was used to install horizontalscreens beneath buildings, streets, and utilities. Ten parallel horizontal wells were installed to inject potassium permanganate (KMNO4) solution. Well screens were between 130 and 330 feet long. Some of the wells were installed in pairs, with screens placed in target zones at 30-foot and 40-foot depths. Aquifer tests were used to evaluate hydraulic conductivity and anisotropy. A three-dimensional, finite difference flow and transport model was used to design well screens and define operational ranges of the injection system, including flow rates and pressures. KMNO4 solution was injected in two phases. In total 140 tons of KMNO4 were mixed to create 1.75 million gallons of solution. The use of horizontal wells allowed Shaw to inject into 10 horizontal wells instead of what would have been 120 vertical wells, and minimized our footprint on the Site. The ability to inject at 10 points into 2300 feet of well screen allowed for a higher injection rate than would have been accomplished using vertical wells. This resulted in our highest injection rate of 1.03 million gallons of KMNO4 solution in a 26-day period. After 6 months the KMNO4 solution remains persistent in the formation and has reduced tetrachloroethene (PCE) concentrations from 12 mg/L to non-detectable levels.

INTRODUCTION
The Site had been a regional shopping center for 60 years, but most of the tenants had
vacated and what remained was the larger Main Parcel with abandoned buildings and a
smaller parcel with an active dry cleaning facility. Sixty years of operations of the dry
cleaning facility had resulted in soil and groundwater contamination at the Site, first
noted in 1994. In 2004, the Site was purchased from the former owners with the intent to
complete a major redevelopment of the Site for mixed commercial and residential use.

SITE SETTING
The Site is located on 35 acres in Maryland overlying the Aquia Formation, a water table aquifer with the depth to groundwater ranging from 15 to 25 feet below ground surface (bgs) at the Site. The dry cleaner is located on the Annex Parcel to the north and across a road from the Main Parcel. The underground utilities around the dry cleaner’s building, the road and its underground utilities near the source area, and utility corridors and building construction in the more downgradient area of the plume were limiting factors that made the use of a vertical injection well system impractical at this Site (Figure1).

FIGURE 1. Site setting.

CONCEPTUAL SITE MODEL
The majority of the dry cleaning solvent was released as a solution through a break in a pipe leading to the local POTW. This pipe break was located directly under the dry cleaning building. Concentrations of PCE in this discharge water were 2,000 mg/L. Concentrations of PCE in the discharge from the dry cleaning distillation unit were as high as 11,000 mg/L prior to mixing with other wastewaters from the facility. In 2004, when Shaw and Losonsky & Associates first became involved, the groundwater plume had migrated 1,600 feet from the source. The highest concentrations of PCE were found at depths of 25 to 45 feet bgs (Figure 2). There was no indication of the presence of a dense non-aqueous phase layer. Soils at the Site are primarily medium to fine sands and silty sands. The groundwater flow direction is to the south-southeast. Groundwater flow rates within this aquifer are 0.2 to 0.4 feet per day. Hydraulic conductivity generally decreased with depth. Soil oxidant demand (SOD) concentrations were determined to be 1.5 to 2.0 mg/L. There was little natural reductive dechlorination occurring even 1,600 feet from the source.

FIGURE 2. Cross-section of groundwater plume.

The placement of a sufficient number of vertical wells in the area of the plume was
impractical due to the presence of streets and underground utilities. The horizontal well
option was then explored.

HORIZONTAL WELL SCREEN DESIGN
The design of the screens for the horizontal wells was performed using modeling efforts to produce a screen pattern designed to achieve even distribution of the KMNO4 solution throughout the length of each horizontal well screen. Aquifer tests provided hydraulic conductivity and anisotropy data. A 3-D, finite difference flow and transport model of the injection wells was used to design the well screens and define operational ranges of the injection system, including flow rates and pressures. The groundwater modeling was performed using Waterloo Hydrogeologic’s Visual MODFLOW version 4.1.0.143. The model code is based on the finite difference method of solving partial differential equations describing groundwater flow. The design specifies the open area of the screen that allows uniform injection of fluid into the formation. This analysis consists of iterative calculations of pipe flow, orifice (slot) flow, and formation flow to generate the following parameters; pressure along the screen, flow through the screened pipe, and incremental and cumulative injection of fluid into the formation. The analysis requires definition of a series of pipe specifications and hydrogeologic parameters and was used to specify optimal operating conditions for each horizontal well. The model simulates the injection fluid moving down the well, through the well screen slots, and into and through the formation. The model provides the necessary open area along the length of the well screen to achieve uniformity of flow. The necessary open area requirements for the 10 wells ranged from 0.0357 to 0.0429 percent open area. Using a standard slot width of 0.02-inch, the required number of slots was calculated for each length of screen.

HORIZONTAL WELL INSTALLATION
Directional drilling technology (Figure 3) was used to install the horizontal wells under utility corridors, buildings, and roads during the early stages of construction of commercial and residential buildings. The horizontal well screens were placed in the heaviest contaminated zones without having to deal with interferences from underground utilities and access issues associated with drilling in public roadways. Well screens were between 130 and 330 feet long (Figure 4). The wells were drilled as blind wells, without exit points. Wells nearest the source were screened at 30 feet bgs. Wells further downgradient were paired to be screened at target zones of 30 and 40 feet bgs (Figure 5).

FIGURE 3. Directional drill rig.

FIGURE 4. Example of longer horizontal well construction.

FIGURE 5. Plan view of horizontal wells.

FIRST INJECTION
In the first phase, 56,000 pounds of KMNO4 were mixed to create 340,000 gallons of 2-
percent KMNO4 solution injected into the 10 horizontal wells. The delivery rate per unit
length of screen was generally uniform. The longest well injected at more than 16 gallons per minute. An HDPE manifold transferred KMNO4 solution to the 10 well heads.

The KMNO4 injection model developed in the design phase of the project was recalibrated using data collected during and after the first injection. Hydraulic data confirmed the accuracy of anisotropy values previously derived from analyses of a vertical pumping test performed in support of the design of the injection system. The first injection indicated zones of delayed arrival of KMNO4 between certain wells. The three-dimensional model was used to simulate the first injection, and assess various alternatives for improved delivery of KMNO4. The difference between pulsed injection, as executed during the first injection phase, and a continuous, 30-day injection of equal volume of KMNO4 solution is illustrated by the injection simulation cross sections in Figure 6. The model simulation shows that the differences between the two injection schemes are minor and appear mainly at the down-gradient edge of the injected KMNO4. The base case simulation of three horizontal wells with variable spacing is shown in Figure 7, along with an alternative injection scenario using vertical and horizontal injection wells. The base case shows a zone of delayed arrival of KMNO4 between adjacent horizontal wells, on the left hand side of Figure 7. The alternative scenario simulation shown on right hand side of Figure 7 uses vertical wells to accelerate KMNO4 delivery. The alternative scenario also illustrates minor adjustments in the distribution of KMNO4 around the horizontal wells, resulting from the vertical well injection. Cross sections of these two scenarios are shown in Figure 8. Comparison of the base case with the alternative scenario shows that the vertical wells fill in the zone of delayed arrival to similar depths as the horizontal wells. Minor impact of a vertical well on the adjacent horizontal well is seen at the downgradient edge of the injected KMNO4. The simulations shown in Figure 9 illustrate the effect of using a combination of horizontal injection and extraction wells. One well on the right hand side of Figure 9 withdraws groundwater while the other two are injecting KMNO4. This allows KMNO4 to spread more quickly into the zone of delayed arrival than in the base case, shown on the left hand side of Figure 9. These simulations of alternative injection scenarios provided valuable information that was considered in planning the second injection phase. During the injection, KMNO4 concentrations were monitored at three depths as shown in Figures 10 and 11.

FIGURE 6. Injection simulation cross sections.

FIGURE 7. Injection simulation and alternative scenario.

FIGURE 8. Base case and alternative scenario cross sections.

FIGURE 9. Injection and extraction simulation.

SECOND INJECTION
In the second phase, 84 tons of KMNO4 were injected into the horizontal wells. Then 30 tons were injected into newly installed supplemental vertical wells. The use of an automated mixing system with two 18,000-gallon mixing tanks allowed the mixing and injection of up to three tons of KMNO4 or 55,000 gallons of KMNO4 solution per shift. The batch process entailed a fire hydrant to put approximately 1,650 pounds of KMNO4 into solution. This would create 10,000 gallons of solution stored in one of the 18,000- gallon mixing tanks. Because of the combined screen length of the 10 horizontal wells, the KMNO4 solution was be pumped from the mixing tank at 115 gallons per minute. At the same time a second 10,000 gallon batch could be prepared. During this second injection, our production rate was maximized so that we were able to inject 1.03 million gallons of KMNO4 solution in a 26-day period.

PERFORMANCE EVALUATION
Monitoring wells were installed to monitor the distribution of the KMNO4 solution as
wells as the PCE concentrations.

FIGURE 10. Visual depiction of injection of permanganate.

FIGURE 11. Injection of permanganate – 90 days later.

SUMMARY
The use of horizontal wells allowed Shaw to inject into 10 horizontal wells instead of 120 vertical wells. This minimized our footprint on the Site and helped to keep our ISCO project going during heavy Site redevelopment work by our client. The ability to inject at 10 points into 2200 feet of well screen allowed for a higher injection rate than would have been accomplished using vertical wells. This resulted in an injection rate of 1.03 million gallons of KMNO4 solution in a 26-day period, our most productive period. The use of horizontal wells resulted in a shorter injection time frame than would have occurred with vertical wells and minimized impacts to our client’s development work and schedule. Horizontal wells screens were determined to be more efficient at distributing KMNO4 into the zone where the highest contamination was present. After more than 6 months the KMNO4 solution remains persistent in the formation and has reduced PCE concentrations from 12 mg/L to non-detectable levels. Our client is completing their Site redevelopment and is scheduled to open this fall.

Posted in Symposium & Conference | Leave a comment

Remembering 9/11: Directional Technologies Aided in World Trade Center Rescue Effort

On Sept. 13th 2001, Kathy Sequino’s telephone rang. It was the New York Department of transportation.

The man on the line had just found Directional Technologies Inc.’s business card ad in the back of Trenchless Technology and he was wondering if Sequino could answer a few questions. He wanted to know if it was technically feasible to drill into the subbasement of the World Trade Center (WTC) using directional drilling technology. He wanted to know if they could bore through concrete walls and tons of steel super structure on the chance that they might locate trapped survivors. He wanted to know if Sequino would help.

The president and owner of Directional Technologies hung up the phone. She conferred with her husband, Mike Sequino, and a few hours later he headed for New York City, 90 miles away.

It had only been two days since hi-jacked airliners full of innocent passengers, had decimated the two WTC towers, symbols of the financial prowess of the Unites States. While most of America, still shell shocked, huddled around televisions waiting for the next bits of news, New York City was busy assembling a elephantine rescue effort for the thousands of missing people.

Directional Technologies was enlisted to help, but the company wasn’t alone. Police, fire and medical personnel along with countless engineers, demolition experts and soldiers were already scouring streets and giving the city support. Amongst these operations, the N.Y. DOT was working on a plan to use a directional drill to burrow through WTC debris in order to insert television inspection cameras and look for victims.

"Directional Technologies, Inc. at World Trade Center ground zero on September 11th, 2001

“They wanted us to drill into the subbasement of the World Trade Center,” said Mike Sequino, vice president of Directional Technologies. “We’ve done something similar for remediation purposes. We had to drill through foundation walls. Once we broke through into the subbasement, we would have to extract the drill, mount a camera to the bottom of the drill pipe, reinsert with the camera and look around for voids and survivors.”

Directional Technologies received support from oil field companies like Schlumberger Oilfield Services, Baker Oil Tools, Houston, Geological Boring, Tacoma, Wash., Frank’s Casing Crew and Rental Tools, Lafayette, La., and television inspect companies like Underground Video, Hillsdale, N.J., Downhole Video, Oklahoma City, Hit Well, Lexington Ky., and CUES, Orlando, FLA. Also helping, companies like UEMSI, Northbrook, Ill., donated television inspection cameras for the rescue effort. Sequino reached New York City that same Thursday night. The surrounding buildings around Ground Zero were still collapsing and crews were unable to get close enough to start the operation.

“It got so chaotic. The first night One Liberty Plaza was still unstable,” said Mike Sequino, “They thought the building was coming down. We didn’t even get to talk to anyone Thursday. The rescue team had to worry about building facades falling. They had to worry about buildings falling.”

Rescue efforts continued Friday and Saturday near Ground Zero, but without much success. The team spoke with fire chiefs as workers removed rubble; then crew was looking for a spot close enough to use the drill. By early Monday morning, around 2:30 early Monday morning, around 2:30 a.m. enough debris has been cleared where a target point was being considered, that target point was the remaining portion of the stairwell in Tower One. The Fire Department of New York Believed according to Sequino that a good portion of the people trying to escaper trying to exit from this location.

“They wanted to get into the stairwell and the only want to do that was to drill through the steel of the super structure. This would require different drilling bits,” explained Mike Sequino. “Digital pictures were sent from Ground Zero to Baker Oil Tools to determine the right drill bit and Ditch Witch quickly made an attachment piece to fit the drill string.” But the debris shifted again and the conditions were simply too unstable to drill though the rubble. Monday and Tuesday, the city re-evaluate its approach. Port Authority engineers and the crew discussed drilling into the mall under the WTC while in the nearby Customs Building, but the building was again too unstable; the noise and vibration might have caused it to collapse. Unfortunately, five days of hope and expectations led to disappointment and a long trip back home.

“We spend five days down there and our guys were burned out, “said Mike Sequino, “Everyone was ready to put anything we needed at our disposal. And that was the one thing that underscored everything. Everyone did everything humanly possible to find any survivors. Firemen, policemen, people from FEMA, everyone risked their lives mulling through the rubble looking for people.”

- Written by Keith Gribbins – TRENCHLESS TECHNOLOGY October 2001

Posted in Articles & Presentations, Directional Drilling | Leave a comment

Horizontal Soil Vapor Extraction

Horizontal Soil Vapor Extraction and Horizontal Air Sparge Well Case Study.
Installation to remediated site closure.

Horizontal Wells allow Rapid Clean-up of R&D Facility Gasoline Release

Background A Research and Development facility in central New Jersey released several thousand gallons of gasoline to the subsurface. Environmental investigations revealed that approximately 80% of the phase separated plume existed below the building. Uninterrupted operation and prevention of vapor intrusion in the facility were key factors that dictated an alternative approach to the remedial strategy. Hudson Environmental Services, Inc. of Matawan, New Jersey completed the remedial investigation, assessed remedial alternatives and proposed a remedy. Horizontal air sparge (AS) and horizontal soil vapor extraction (SVE) with vapor treatment utilizing catalytic oxidation was the recommended and selected remedy.

The Challenge Presented Two technical approaches were available for the horizontal air sparge (AS) and horizontal soil vapor extraction (SVE) system orientation: install a series of multiple vertical wells (a number would be required inside the building) with an interconnecting subsurface piping network, or install three horizontal wells, which would pass beneath the building. Feasibility and financial analyses indicated that the horizontal well system would not disrupt business operations, be less expensive and more efficient than the traditional vertical well approach. Directional Technologies, Inc. was engaged to install the horizontal wells.

Directional Technologies at Work: Our Solution Pilot testing and subsurface characterization provided data enabling Directional Technologies to design two horizontal air sparge wells and one horizontal soil vapor extraction well. The horizontal air sparge and horizontal soil vapor extraction wells were designed to operate at 250 cubic feet per minute (CFM). The system design included a catalytic oxidizer to destroy hydrocarbon vapors extracted from the horizontal soil vapor extraction well.

The NJ Department of Environmental Protection (NJDEP) approved the remedial design following the first design submittal. Underground utilities, building footings and other subsurface structures were identified and surficially marked out prior to well installation. Directional Technologies designed the horizontal well trajectories to avoid these buried structures.

Directional Technologies used a Ditch Witch Directional Boring System to directionally drill the horizontal wells and has used this drill rig to successfully drill bores up to 12 inches in diameter and 700 feet long; while compact in size, it is extremely powerful. The directional drill rig’s compact size allows it to be used in relatively confined areas and the rubber tracks exert minimal ground pressure, minimizing risk of damage to pavement and turf. The power and two speed spindle rotation capability enabled the rig to successfully penetrate both hard and soft soil conditions encountered at the site (fine sands, silts and clays).

Directional Technologies advanced each pilot hole to the specified depth and horizontal termination point using a spade bit. Drill bit X-and-Y axis directional control and operational temperature was provided by a hand-held surface walk-over radio detection instrument. The instrument receives continuous radio signals from a battery-powered instrumentation module contained in a length of drill pipe located directly behind the drill bit. Regularly measuring drill bit temperature is important to ensure that drilling fluids are circulating through the drill bit, especially when drilling in rock. Directional Technologies enlarged each pilot hole to a diameter of 6.5 inches using a spiral-cutting-configured back reamer drill bit designed to minimize formation displacement and compaction. Cement grout pumped through tremie pipes formed a seal in the annular space between the riser and formation.

Directional Technologies developed the horizontal wells with water and a proprietary additive to flush out drilling fluid that may have entered the formation during the horizontal drilling process. Directional Technologies installed two identical horizontal air sparge wells configured as follows: 4 inch diameter, riser length: over 500 feet, screened interval: 260 feet, installed depth: 22 feet below ground surface, 7-9 feet into the water table. The single horizontal soil vapor extraction well was configured and installed as follows: 4 inch diameter, riser length: over 480 feet, screened interval: 240 feet, installed depth: 8 feet below ground surface (5-7 feet above the water table).

The horizontal wells were constructed of SDR-11, a high density polyethylene (HDPE) product; Directional Technologies validated the choice of this choice product via detailed computer modeling. Modeling further dictated the need for multiple slot-zones in the horizontal soil vapor extraction well screen due to the multiple design goals of uniform air sparging and extraction and a flow rate of 250 CFM to the catalytic thermal oxidizer.

Results that Reward The time required to achieve site remediation can be conservatively calculated from the quantity of oxygen delivered to the site by the remediation system. Directional Technologies designed/installed each horizontal air sparge well to deliver approximately 2 pounds per minute of oxygen to the subsurface, or a total of 4 pounds per minute. At this oxygen delivery rate Directional Technologies estimated that site cleanup would be accomplished in approximately one year. The horizontal air sparge and horizontal soil vapor extraction system operated from March 1999 to October 2000 and removed approximately 17,000 pounds of gasoline. The separate phase gasoline plume under the building was completely eliminated. This resulted in the NJDEP approving” no further action” for soils.

Contact Directional Technologies, Inc.
Horizontal Directional Drilling Services
Kathy Sequino
ksequino@directionaltech.com
203-294-9200

Posted in Articles & Presentations, Horizontal Soil Vapor Extraction | Tagged | Leave a comment

Benefits Of Horizontal Wells

BARRIER AIR SPARGING

Why Air Sparging?

Quick Refresher: air sparging (AS) is a proven groundwater remediation technique that removes volatile organic compounds (VOCs) from groundwater by injecting air into water-saturated formations. There are two common approaches to AS. The first involves injecting air through wells into the impacted area to remediate the plume. The second creates a transport barrier by sparging downstream from the impacted zone, VOCs are removed as the groundwater passes through the sparge barrier and aeration enhances natural attenuation.

How are Barrier Air Sparge Systems Usually Installed?

There are three principal methods: vertical wells, horizontal wells and horizontal trenches.

How Do Vertical Wells and Horizontal Trenches Fall Short? One must ensure there is appropriate overlap to account for radius of influence (ROI) limits with a vertical well network to avoid breakthrough. Vertical well networks require interconnecting piping which can be costly to install and cause expensive business interruptions in commercial areas. There are practical limits to the number of vertical wells that can be networked due to piping friction losses and blower sizing requirements. Horizontal trenches involve depth limitations related to readily available excavation equipment and the potential for expensive business interruptions.

 

Horizontal AS wells typically have 20-40' perpendicular ROI on each side of the well screen.



1,000 foot AS Barrier well

installed at a depth of 23'

to protect Lake Michigan.

HRW directionally drilled by

Directional Technologies, Inc.

 

How Can Horizontal Wells Enhance The Barrier Sparging Process?

Horizontal wells typically have a robust radius of influence if properly designed. Directional Technologies uses a proprietary screen design methodology to ensure uniform air flow across the screen length. Horizontal wells can be designed to effectively protect extensive areas. For example, Directional Technologies recently installed a 1,000-foot long horizontal well to serve as an AS barrier at a site adjacent to Lake Michigan in Waukegan, IL. Horizontal wells do not involve complicated interconnecting piping networks – connect your surface equipment at one location. In addition, horizontal wells can be “stacked”, if required, to provide a deeper barrier. In other words, two horizontal wells could be installed one on top of the other (appropriately spaced to ensure overlapping ROI) from essentially one drilling location. Finally, horizontal wells can be configured to avoid expensive business disruptions in commercial locations typically associated with vertical technologies.

Directional Technologies Installs Horizontal Wells!

 

Directional Technologies has been successfully installing horizontal wells since 1984! The companies' experience in the oil field, environmental remediation industry and utility industry allows us to complete projects that were previously considered unfeasible. Give us a call to discuss your next AS system project.

For additional information

contact Kathy Sequino

203-294-9200

Posted in Articles & Presentations, Horizontal Wells | Tagged | Leave a comment

Directional Technologies, Inc. conducts unique horizontal remediation well installation in Railroad Yard

Background

horizontal-remediation-well-installThe Long Island Rail Road (LIRR) Morris Park Yard, located at the Intersection of Atlantic Avenue and 121st Street in Queens, New York, is a historic rail yard with one of the few remaining operational turntables in the USA. The Morris Park Yard has been used to repair and refuel locomotives for over 100 years and continues to serve one of the nation’s busiest regional rail lines. Locomotive refueling operations over many decades resulted in significant subsurface petroleum hydrocarbon releases.

The Challenge Presented

On behalf of LIRR, Franklin Environmental developed a remediation plan to address subsurface non-aqueous phase petroleum hydrocarbons, in compliance with regulatory requirements. LIRR selected in situ bioremediation as the remedy for the hydrocarbons located at and above the water table. Bioamendment fluid was to be introduced into the subsurface by some means that allowed infiltration into the hydrocarbon-impacted vadose zone. The area requiring remediation was covered with a dense network of railroad tracks and the hydrocarbon target depth was less than four feet below ground surface. The narrow corridors between railroad tracks did not allow installation of vertical injection wells and interconnecting piping.

Directional Technologies, Inc. (DTI) met with LIRR officials and Franklin environmental professionals to discuss the project. Neither Franklin nor LIRR had any prior experience with directional drilling technology and its capabilities. DTI was challenged with: 1) convincing an unsure client that we could safely and successfully execute the program via directional drilling methods; and 2) installing the horizontal remediation well network without disrupting the busy rail yard.

Directional Technologies at Work: Our Solution

LIRR engaged DTI to design and install 17 entry/exit horizontal wells for Bioamendment injection and 10 utility conduit crossings under the busy tracks in the rail yard. Our team designed the wells to inject high-viscosity Bioamendment solution uniformly along the length of the well screens to saturate the vadose zone soils above and below the screen horizon.
DTI initially set up its drilling equipment near the location where a new remediation system equipment building was being constructed and advanced an array of well and conduit bores from that location. horizontal drillingAs the drilling program progressed, our client: 1) quickly learned about the many unique capabilities of directional drilling technology, such as the ability to “steer” the drill bit in the vertical and horizontal axis and accurately measure/detect bit location 2) saw that the borings were being successfully and safely installed without interrupting rail yard operation; and 3) soon became convinced that they had made the right decision to engage DTI for this very challenging assignment.

The horizontal wells passed beneath multiple busy railroad tracks where locomotives were fueled and serviced. The bore paths were carefully installed using subsurface steering-while-drilling techniques to avoid underground water, sewer, power, communications, and gas lines at depths very close to the bore paths. As the bore holes were advanced at Bioamendment injection targets depths, it was necessary to increase the borehole depths beneath track sections to meet LIRR geotechnical track protection standards. This procedure produced undulating bore paths that required precise directional drilling control to install the horizontal wells correctly. Complex intersecting utilities at several locations exercised DTI’s proven ability to successfully combine subsurface directional drilling with surficial trenching to complete the bore paths.
DTI’s drilling schedules was closely coordinated with railroad operational schedules, allowing locomotive engine repair and refueling operations to continue uninterrupted during the six-week well installation program. DTI deployed its equipment in the narrow between-track corridors such that drilling operations were safely executed even as locomotives passed nearby.

Results that Reward

DTI safely completed this challenging assignment on schedule without interrupting the busy rail yard.

Posted in Articles & Presentations, Horizontal Remediation Wells | Tagged | Leave a comment

Horizontal Air Sparge Wells Solve Access Limitations Beneath Air Field Tarmac

Horizontal-air-sparge-wellsAir Force Base tarmac is a double-edged sword with respect to environmental remediation. Concrete thicker than at commercial airports virtually eliminates infiltration and limits migration of jet fuel constituents in groundwater, but source material in the vadose zone remains indefinitely, extending the life of the groundwater plume. Horizontal air sparge wells are an effective means of addressing both saturated and unsaturated hydrocarbons beneath airport or air field tarmac, but they cannot be installed unless the drilling contractor can overcome a barrage of challenges, including:

  • Flight line traffic and work restrictions,
  • Limited site access to work areas, and inability to place and operate drilling equipment on the tarmac,
  • Aircraft noise,
  • Signal interference to the drill head locating system caused by tarmac concrete and subsurface utility banks, allowing only highly trained and experienced horizontal well drilling specialists to keep the wellbore on target,
  • Frequent interruption of the work schedule to accommodate aircraft, and
  • Strict adherence to workday schedules.

Directional Technologies, Inc. successfully overcame all of these challenges while installing four horizontal air sparge wells at an Air Force facility in the southeastern United States. The wells fan out over a span of about 120 degrees from a central drilling rig area, so the wells were like spokes of a wheel. Each well placed 150 feet of screen at 25 feet below the tarmac surface. The wells were drilled without exit points, and the tarmac remained free of excavation or any other invasive drilling-related activity. The tarmac was accessible for short periods of time for surveying purposes, and Directional Technologies developed a drilling program that accommodated limited, controlled access along most of the drill path. In spite of these limitations, the client received detailed as-built diagrams of the well paths and profiles.

air-sparge-wellsLocal hydrogeology added to the challenges met by the Directional Technologies’ experienced drilling team. Heaving sands along portions of the well paths caused differential sticking of the drill string and well casing during drilling and installation. The drilling team resolved the problem efficiently by adjusting the drilling fluid program and completion method.
All four wells were completed with 3-inch schedule 10s slotted stainless steel screen. The screens were slotted longitudinally, with slots parallel to the axis of the pipe. Longitudinal slots were chosen to maximize pipe strength and air flow distribution. The slots were 0.011 wide, providing filtration control for the fine to medium sand in the target zone.

Posted in Articles & Presentations, Horizontal Wells | Tagged | Leave a comment

Radial Horizontal Well System Targets Specific LNAPL Viscosities in Multiple Product Plume

horizontal well

Directional drilling rig tucked in corner while normal business activities continue

A multiple product plume under an active paint facility includes No. 6 Oil, No. 4 Oil, mineral spirits and lube oil. Contrasting viscosities can cause preferential flow, complicating LNAPL recovery efforts that are required by the state environmental agency. The plume is under a building, and installation of vertical wells would be costly, not only because of the large number of concrete pad penetrations and conveyance pipe installation, but also because it would interrupt operations of the active business. Six horizontal wells were installed instead, radiating from a central drilling location in the shipping department. The central drilling location kept the footprint of drilling operations to a minimum, and the six horizontal wells were installed as blind wells, like spokes of a wheel. All six wellbores were drilled through a 20-by-10-foot, decommissioned underground storage tank beneath the central drilling location, and the wellheads were completed within this tank, conveniently placing surface equipment for all six wells, including piping and oil-water separation, inside the tank. Since the wells were drilled blind, there was no need to exit at ground surface at the far end of the wells. Instead, each well terminated in the target zone at the distal endpoint of the well screen, eliminating unnecessary drilling and surface construction.

The wells were completed with 6-inch, schedule 80 PVC pipe, with conventional slots appropriate for LNAPL recovery. Each well was equipped with a down-hole pump that can easily be moved to the optimal location for efficient LNAPL recovery. The ability to adjust the pump location along the horizontal screen allows continuous optimization of recovery in response to changing positions of the multiple LNAPL phases with contrasting viscosities. This flexibility avoids or greatly delays the need for installing new well points that are often required in vertical LNAPL recovery well fields as the LNAPL distribution changes.

Directional Technologies, Inc. (DTI) installed the 6 wells, with over 200 feet total of screen, in less than two weeks. Forklifts moved unimpeded during those two weeks, allowing the shipping department to continue business as usual. Operation and maintenance of the LNAPL recovery system will likewise not impede operations at the paint facility. The centralized location of surface equipment in the underground tank at the center of the “wheel” of horizontal recovery wells will cut the time required for O&M activities to a fraction of what would have been required for an equivalent vertical well LNAPL recovery system dispersed within the building.

Posted in Articles & Presentations, Horizontal Wells | Tagged | Leave a comment

DTI Installs 3 Blind Horizontal Remediation Wells in Cobble

The Issue

horizontal remediation well

An active retail gas station next to a wetland area has benzene and trimethylbenzene plumes in a water table aquifer containing sand, gravel and cobbles. Rock fragments and boulders several feet in diameter lie in the vadose zone, between the ground surface and the water table. Business at the gas station would slow down or stop for an extended period of time if a vertical air sparge and soil vapor extraction wells had to be drilled through the rock because the wells would surround the pump island, block the driveways, and even interfere with access to the store itself. The vertical wells would have to be closely spaced because of their limited zone of influence.

The Solution

As a national directional driller based in New England, Directional Technologies, Inc. has the experience to complete projects that may confound other companies. New England is known for its tough subsurface conditions and the company has been installing conduits and horizontal wells in gravel, cobbles and rock since 1992. Directional Technologies installed three blind wells—two air sparge wells and one soil vapor extraction well under the pump island, driveways, and even under the retail store—within a week. Blind wells have only one wellhead, avoiding the need to exit through the wetland area, and limiting the amount of drilling through boulders in the vadose zone to three riser sections (one for each well). Cars pumped gas while the directional wellbore was advancing beneath the pump island and driveways. horizontal remediation wellCustomers roamed the store aisles and paid at the cash register even as the drillers were locating the advancing drill bit 20 feet beneath the floor. The project was completed on time and without a change order request, despite the need to adjust well entry points, paths, screen depths, and completion details.

The Technology

Directional Technologies brought a variety of excavation and drilling equipment to the site to be prepared for any obstacles to drilling. Limited excavation around the wellheads allowed the driller to coax the drill rod through the rock-strewn vadose zone layers. The well screens were drilled beneath the layer of boulders, and the specialized drill bit navigated through cobbles and rock fragments in the target zone. Placement accuracy was achieved with the use of a walkover locating device which allowed the experienced operators to narrow down the location of the drill bit in the midst of interfering subsurface utilities, tanks, and the foundations and flooring of the retail store. Directional Technologies customizes the drilling fluid for subsurface conditions at every job site. The wellbore remained stable during drilling and reaming through the cobbles and rock fragments, and Directional Technologies successfully installed up to 230 feet of completion pipe in each of the three blind horizontal wells.

Posted in Articles & Presentations, Horizontal Remediation Wells | Tagged | Leave a comment

Plume Control under a City Building – Vapor Intrusion Mitigation

subsurface remediation wellSubsurface remediation in a big city setting is complicated. Limited work space, heavy traffic, noise restrictions, and a dense network of utilities are just some of the factors that conspire to make the installation of any in situ plume control or plume reduction system a seemingly unsolvable logistical puzzle. Horizontal wells placed directly beneath a building can provide protection from soil and groundwater sources of vapor intrusion, and are more effective for plume remediation than wells that are placed down-gradient or up-gradient of the plume just to avoid having to drill wells inside the building.

Directional Technologies, Inc. has mastered this puzzle over many years’ experience working in big cities in the northeast and throughout the USA. An example of this is in New York City, near the boundary between Yonkers and the Bronx, where a former paint plant leaked mineral spirits into soil beneath a building that is currently used by ExtraSpace for public storage. Besides being under a large portion of the building, the groundwater plume extended outside, under a railroad track, and entered a nearby stream.

horizontal remediation well drillingA combined SVE and groundwater extraction system was installed using three horizontal wells: one SVE well and one groundwater extraction well under the building, and one groundwater extraction well outside the building, along the railroad track. Directional Technologies, Inc. completed all three wells with four-inch stainless steel wire-wrapped
screen. The wells under the building have 50-foot long screens, and the well along the railroad track has a 100-foot long screen. All three are “blind” wells, with riser extending from only one end of the screen section, while the other end of the screen terminates under ground.

Directional Technologies, Inc., is an industry leader in the installation of blind wells. The soil vapor and groundwater extraction wells under the building are 5 and 22 feet deep, respectively. The wells have 50-foot long risers, demonstrating Directional Technology, Inc.’s expertise in minimizing riser length, which was crucial at this site because the wellheads needed to be inside the building. The outside well has a 170-foot long riser in order to accommodate both screen placement and wellhead location requirements.

The wells have performed to the satisfaction of the site owner and New York State Department of Environmental Conservation. The SVE well developed a symmetrical zone of influence extending at least 50 feet away from the well. The groundwater extraction well under the building depressed the water table beneath the building, creating a trough of depression that increased the distance between the water table and the building slab. The well outside the building provides hydraulic control, preventing impact to the nearby stream.

Directional Technologies, Inc.
203-294-9200
ksequino@directionaltech.com
www.directionaltech.com

Posted in Articles & Presentations, Vapor Intrusion Mitigation | Tagged | Leave a comment