• Facebook

  • Twitter

  • LinkedIn

  • YouTube

  • Over 1,000 Wells

    Over 1,000 Horizontal Remediation Wells Installed
  • Geographic Reach

    Geographic Reach: Worldwide
  • Chemical Oxidation

    Chemical Oxidation with Horizontal Wells

    A major urban high-rise development project in Annapolis MD required in-situ treatment of dry cleaner solvents. Ten horizontal wells were drilled under an active construction site for potassium permanganate injection. The system was installed in four weeks without disrupting ongoing construction of building and roads. The horizontal well system has successfully injected 1.3 million gallons of oxidant solution. Several injection events occurred while high-rise construction continued at the site.

    For more information on this project, please follow this link to the two papers presented at the Battelle Conference in May of 2008 – Proceedings of the Sixth International Conference on Remediation of Chlorinated and Recalcitrant Compounds: Enhanced Delivery of Potassium Permanganate Using horizontal wells . W.M. Moran, Achieving Delivery Goals with Engineered Screens. M.J. Sequino